Please be advised that the Site Services Department will be overseeing multiple paving projects within the coming weeks.
We will be repaving sidewalks in the following areas:
- Around the Rensselaer Student Union
- West Lot
- Albright Lot
- All sidewalks surrounding Albright
- Cook Drive, from the circle in front of the Houston Field House to the intersection of Sunset Avenue
- Sidewalks between the buildings in Stacwyck
Schedule Overview (Weather Permitting):
- July 16–18: HMA will be on site working on the Union, Albright, and potentially the Stacwyck sidewalks.
- July 30–August 1: Milling will take place around the Union, Cook Drive, Albright, and West Lot.
- August 4–6: New pavement will be laid in all designated areas.
Please note that these dates are subject to change based on weather conditions.
We will continue to provide updates as the project progresses.
Questions or concerns can be directed to Fixx or directly to Matthew Robinson: robinm10@rpi.edu